How to calculate construction job costs
The example covers two shifts by one worker, machine hire and a material delivery on a fictional community centre extension. All figures are in Czech crowns, excluding VAT, and cover the position after those two shifts.
See how the working hours were calculated
Two shifts on the Javor extension
| Item | Calculation | Cost |
|---|---|---|
| Labour | 15.5 h × CZK 365 | CZK 5,657.50 |
| Machine | 2.5 h × CZK 640 | CZK 1,600.00 |
| Materials | 1 delivery | CZK 3,400.00 |
| Total | CZK 10,657.50 | |
How much is left to invoice?
A contract value of CZK 30,000 less CZK 12,000 already invoiced leaves CZK 18,000 to invoice. The contract value less costs recorded so far comes to CZK 19,342.50. Further work and deliveries will reduce that amount.
Where the figures come from
Take working hours from the timesheets after deducting breaks. Check the labour and machine rates in force on the date of work. Count each material invoice once. Fill in missing rates before using the overall cost.